Shelborn Schedule of Works
Tap any field to edit. Use + Add space to extend, Save as HTML to keep a working copy with all your data, and Save as PDF to issue.
Cosmetic Refresh Programme

58 Waterloo Street, Glasgow

Office suites & common staircase — detailed schedule of works & cost plan

Prepared for
Shelborn (Mark Rabinowitz, Brian Rabinowitz)
Project manager
Graham Black — Catalyst Consult
Cost plan basis
Catalyst cost plan, 18 June 2026
Status
Draft — for sanction
Target completion
Mid-August 2026
Works total (exc VAT)
£0
Incl. fees & contingency · exc. kitchens & staircase
Blended rate
£0
per sq ft across let-able suites
Priced suites
0
Auto-numbered — add or remove
Contingency
£
Fixed allowance within the total

Project team

People involved

Add or remove anyone on the project. These names drive the owner dropdown on each item under “Next steps”.

Contractors

Subcontractors & trades

Add each contractor on the job, then allocate every priced line in the breakdowns below to whoever is carrying it out (the dropdown under each cost line). Once a space is set to Approved, you can issue that contractor a one-page, client-named instruction to proceed — showing only their allocated works in the approved spaces, with their costs, and a sign-off for both parties. Nothing else from the project is included.

Works by space

Spaces are numbered automatically in order. Each shows the priced trade breakdown, scope, decision/hold notes, options and image sets. Figures exclude VAT.

Common staircase & lift lobbies

Kitchens — decision & budget

Kitchen strategy

Kitchens are excluded from the £95,811 cost plan and are a separate lettability decision. Units in 1-A, 1-B, 4-A, 4-C and 5-B are all serviceable; the question is which to upgrade. A full replacement is at least ~£5,000 per kitchen; a bespoke / higher-spec refit runs ~£12k–£15k (ref: 124 St Vincent Street ~£15k each incl. zip tap ~£1,600). Dream Doors quoted ~£20k–£25k to reface. Standardise finishes and matching units; remove islands where unnecessary (favour bench seating); tailor base-unit counts to expected staff numbers; consider a coloured splashback overlay + modern downlights (~£150/fitting) for 4-C rather than a full strip-out.

KitchenApproachBudget (exc VAT)
Kitchens sub-total£0

Furniture & letting strategy

Approach

  • Fit out the easiest-to-let suites first — those with the best natural light — so a viewer walks in and can sign immediately.
  • Prioritise fully-fitted offering in 1-A, 4-A, 4-C and 5-B. Add furniture elsewhere within about a week once a tenant commits.
  • 1-A furniture: treat both rooms as meeting rooms (larger + smaller tables) plus banks of desks — roughly two banks of eight (~16 workstations).
  • Furniture can be ordered and delivered within ~1 week, so it need not gate the build programme.

Programme & commercials

  • On-site start: possible next week once formal sanction is given.
  • Target completion: mid-August (pull earlier where feasible).
  • Payment: subcontractors require payment up-front or guaranteed within 7 days.
  • Labour: Catalyst manage all trades; Graham has decorator & carpenter contacts; Mark to share the Framework decorator details.
  • Building warrant (Level 2-B): required for the subdivision + breakout/kitchen; G53 to lead, ~4–6 weeks — hold related works pending decision.
  • ICT: Moishe to visit and check the IT & data provision.

Open decisions & next steps

Decisions to close out

    Next steps

      Cost plan summary — reconciliation

      Reconciles to the Catalyst cost plan of 18 June 2026: £95,811.10 + VAT, £6.68/sq ft, excluding kitchens and the staircase / lift lobbies. Any lines you add that aren’t one of the six standard trades are grouped under “Other”.

      Works programme

      Auto-generated from the approved spaces. Approve a space, then set its Proposed start and Duration in that space to place it on the programme. Each bar shows a works package — where (which space, with its trades) and when it runs. Hover a bar for the full dates.

      Shelborn Asset Management · Commercial Property Investment & Development
      All figures exclusive of VAT and stated in £ sterling. Trade costs obtained by Catalyst directly from subcontractors; Catalyst to manage all trades on site. New-carpet allowance based on £20/m² supply & lay. Working document derived from the Catalyst cost plan (18 June 2026), the photographic works schedule (9 June 2026) and the project call. Edits, images and links are held in the page. Use “Save as HTML” in the toolbar to download a working copy with all your data baked in (re-open it to keep editing), or “Save as PDF” to issue (embedded images increase the file size).